Monday, August 31, 2009

By the dawn's early light ...



A major milestone was met in the early morning hours on Friday, August 28th, when the crews began pouring the concrete slab for the first floor of the parking garage. Over 150 cubic yards of concrete were poured for both the slab and a portion or the ramp that will lead to the 2nd floor parking level. Work has begun on the forms for additional ramps, columns, and beams in preparation for the elevated slab of the next floor. The top photo shows the pre-dawn pour in progress, and the middle photo shows the concrete finishing crew still at work. The bottom photo shows how the site looked in March before the foundation pilings were started.