Monday, August 31, 2009

By the dawn's early light ...



A major milestone was met in the early morning hours on Friday, August 28th, when the crews began pouring the concrete slab for the first floor of the parking garage. Over 150 cubic yards of concrete were poured for both the slab and a portion or the ramp that will lead to the 2nd floor parking level. Work has begun on the forms for additional ramps, columns, and beams in preparation for the elevated slab of the next floor. The top photo shows the pre-dawn pour in progress, and the middle photo shows the concrete finishing crew still at work. The bottom photo shows how the site looked in March before the foundation pilings were started.

Monday, August 10, 2009

Bird's eye view




In the bottom photo, taken at the end of May, the pilings have been driven and the site has been cleared and made ready for work on the structure to begin. The top photo, taken at the end of July, shows the significant progress that has been made in just a little over 2 months. The footprint of the building is beginning to emerge, and soon the slabs for the first floor will be in place.

Thursday, August 6, 2009

Electrifying progress


This photo shows the electrical feeder conduits that will bring power into the Cancer Center from a large step-down transformer to be located along the South Claiborne side of the site. The 24 conduits, installed by Frischhertz Electric of New Orleans, total about 1.4 miles (7,200 feet) just to bring the power from the street to the building. Concrete will soon be poured into the wooden forms to encase the conduit and protect it from damage.

Meanwhile, concrete wall, column, and grade beam installations continue along with storm water and sanitary piping. Fire pump infrastructure is being placed, and the elevator pits have been completed.

Monday, August 3, 2009

A Strong Foundation



The large monolithic pilecaps have been completed, and over 2,800 yards of concrete have been poured in the pile caps, walls, and columns. While construction of the concrete forms and steel for the shear walls and columns continues (Top photo), communications and electrical duct banks are being installed (Bottom photo) along with sanitary and storm drains. Manpower on the site has increased to sixty-five. A 63% increase from last week.