Sometimes the work site doesn't appear to change much week-to-week so let's take a look at the numbers. They show how well we are moving forward:


250 Tons of rebar steel have been placed to date.

8,400 yards of spoils hauled off.

2,300 yards of fill placed.

1,800 yards of Concrete placed.

27 pile caps for the main building structure completed along with 15 Large columns and 10 small columns


Man power is increasing and the current estimated head count of workers is in excess of forty (40) workers in the field


Brice has started installing building grade beams, concrete material and forms are in place as this activity will continue for many weeks ahead. Completion of large monumental pile caps is expected very soon weather permitting, and first floor underground preparatory work has begun- all electrical, communications and plumbing systems supporting the first floor will be complete before the end of August .